Most of the problems observed on the shop floor are symptoms of underlying problems in the layout, the material flow, or the way the line was originally designed. When these fundamentals are no longer aligned with production demand, operators are forced to compensate for system shortcomings rather than being supported by a stable and capable process. This was the situation at VDL Bus Eindhoven when the new generation of bus modules entered production. A single mixed model line, long travel distances, unbalanced workloads, and frequent operator workarounds made the work significantly more complex than necessary. This situation triggered a comprehensive redesign of the production flow — starting at factory level and subsequently refined in detail. This case describes how the team untangled the layout, restored flow, and used the Assembly Line Design Suite (ALD) to rebuild the line with clarity and precision.
Introduction
When the plant manager started at VDL Bus Eindhoven, one of the first things he observed was the limited extent to which the factory layout supported the actual flow of work. “If you’d drawn a spaghetti diagram of how everything came in and went out,” he said, “you’d see immediately that the flow was completely illogical.” Modules travelled long distances through the hall without value being added. Although this initial assessment was not yet supported by detailed data, the signal was clear. “The situation was misaligned with effective flow principles and required structural change,” he thought.
“The situation was misaligned with effective flow principles and required structural change.”
To remain competitive in the market, the urgency to improve this intensified. The factory required a substantial improvement in efficiency rather than another cycle of isolated, local optimizations. The stakes were high. The first buses required far more hours than the business could sustain, and the organization committed itself to a significant reduction. Realizing this reduction was a key condition for achieving long‑term profitability.
Before any detailed design work, the team made two decisive moves after the initial analysis. First, the single assembly line producing all possible variants was divided into three mixed‑model lines to reduce complexity and improve balance. Second, they rotated the entire layout ninety degrees to straighten the overall material flow.
Two advantages were considered as most critical. The first addressed a persistent logistics bottleneck: a continuous conflict point where incoming and outgoing goods intersected. As observed, the logistics team was operating in a constant state of pressure due to handling incoming and outgoing materials. “By rotating the assembly lines, we could create a separate in and outflow and finally generate real product flow.”
The second reason was leadership. Previously, team leaders were responsible only for fragments of the line. During daily production meetings, delays were always someone else’s fault. “By splitting up and rotating the lines, a team leader became responsible for the entire line from start to finish. ”
With the factory level flow restored, and clear visual management in place, the team could finally address the real challenge: redesigning the assembly logic itself. As one engineer put it: “Once the layout made sense, we could finally start designing the work instead of fighting the system.”
A New Way of Designing the Line
With the physical flow untangled, the next step was to redesign the work itself. This was the moment the team shifted from factory level decisions to task level clarity — from “how the product moves” to “how the work is actually done.”
“Before, we were arranging stations. Now we’re designing assembly logic.”
Before redesigning the assembly lines, we focused mainly on the employees’ competencies and less on creating a streamlined process.” That changed completely with the new approach. The team now starts by questioning everything from the start, breaking down every task, capturing what it involves, and documenting it immediately. “We look at the build sequences, we identify the required tools, and we set a standard time based upon time study, and whether logistics can support it,” he explained. “From that basis, you can actually design and manage a line.” “We even now consider moving tasks based on the availability of expensive tooling. We simply take more parameters into account,” his colleague added.
The shift was not only technical — it was also cultural. “ALD forces you to look at the factory in an integrated way,” one engineer said. “Before, line balancing was Engineering’s responsibility and efficient delivery was Logistics’ job. Now those two worlds are tied together. You can’t improve one without the other.”
“ALD forces you to look at the factory in an integrated way,”
And crucially, everything is recorded. “The knowledge existed before, but it was documented in several, separate files.” one engineer said. Now we have a tool that brings everything together and keeps it usable. That’s a real step forward. If production volumes change, we can easily calculate and evaluate a new scenario.”
“And the visual representation of the line design in the tool also enhances employees’ understanding and engagement,” they added.
Working With the Assembly Line Design Suite (ALD)
The engineers described ALD as surprisingly intuitive. “At its core it’s an Excel file,” one of them said. “If you understand how Excel thinks, you get the hang of it quickly.”
Every parameter — tasks, tools, times, predecessors — lives in its own table, all linked together. “Once you’re in that logic, it works pretty smoothly,” he said. You do have to be more careful than in an ERP system. An ERP system protects you with rigid structure, but it simply doesn’t have the functionality and flexibility the ALD Suite offers.
“It’s the first time we’ve had one place where the whole line lives, and based upon actual data from the genba.”
Build sequences defined through PERT relationships became essential. “They show exactly whether a task can or cannot be done at a certain moment,” one said. Task positions were another breakthrough — seeing which tasks naturally belong together because they happen in the same area on the assembly workstation.
The Impact on Productivity and the Shop Floor
The combined effect of the layout redesign and the ALD driven line design was substantial. Productivity improved significantly — a step the plant manager described as “enormous.”
He emphasized that the improvements were not driven by layout and line balancing alone. Additional improvements came from targeted ergonomic investments, including mobile tooling boards, height‑adjustable assembly tables, and two-bin systems for most components across the assembly lines.
“Once the flow made sense and the work was structured, productivity improved significantly.”
“The moment we stopped accepting workarounds as normal,” he said, “the whole atmosphere changed. People could now focus more on building instead of compensating.” The goal was simple: operators should never have to wait!
The engineers saw the impact as well. “The product is built more efficiently, and the workload is now more equally distributed between workstations and operators.”
Before ALD was used, volume changes or takt adjustments were handled in a less detailed way. “Now we can easily calculate a new scenario.”
Looking Ahead
The engineers see clear opportunities to use the tool for future improvements. “The ALD suite is now a significant part of our continuous improvement program.”
“The ALD suite is now a significant part of our continuous improvement program.”
When asked how they would describe ALD to others, one of the engineers underlined that the strength lies in the combination of detail and overview. “Because of the detail, errors or problems surface immediately, while at the same time you keep oversight of the entire line.”
His colleague’s answer was immediate. “If you really want insight into every task and every part of the product you’re building,” he said, “ALD shows you what you’re doing, and how you should do it .”